【单选题】You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week perio.As of today, you've spent ¥260,000 of your budget to complete work that you originally expec...
【简答题】•You are a Project Team Leader. You have had to cancel your next project meeting because some of the members of your team will be abroad. •Write a memo to your project team: •informing them of the can...
【单选题】● You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally e...