【单选题】
某项目建设投资为7830万元,项目建设期为两年,第一年计划投资使用比例为40%,其余为第二年计划投资额,建设期年平均价格上涨率为6%,则该项目建设第二年的涨价预备费应为( )。
A.
356.15万元
B.
264.60万元
C.
547.72万元
D.
580.67万元
手机使用
分享
复制链接
新浪微博
分享QQ
微信扫一扫
微信内点击右上角“…”即可分享
反馈
参考答案:
举一反三
【单选题】请使用曼彻斯特编码规则将下面的电压信号转换成二进制数:
A.
01011010
B.
10110101
C.
00110101
D.
11001000
【多选题】以下哪些正确表示海平面处水的沸点温度()。
A.
373.15 K
B.
273.15 K
C.
273.15°C
D.
373.15°K
E.
212°F
F.
100°C
【单选题】One way to ensure that the circular wait condition never holds is to ____________
A.
impose a total ordering of all resource types and to determine whether one precedes another in the ordering
B.
to never let a process acquire resources that are held by other processes
C.
to let a process wait for only one resource at a time
D.
all of the mentioned
【单选题】甲乙两家公司必须指定牵头人,并授权其代表所有联合体成员负责投标和合同实施阶段的
A.
对外联系工作
B.
签约、审批工作
C.
合同谈判工作
D.
主办、协调工作
【单选题】Company.com is ordering a new p5-570 and planning for the option of using Capacity on  Demand to activate additional resources in the future. Which of the following is a prerequisite to support the ad...
A.
Use Micro-Partitioning
B.
Configure a Virtual I/O Server
C.
Configure dynamic logical partitions
D.
Activate Advanced POWER Virtualization
【单选题】What tool is used to estimate the hardware server resources required for an IPCC Express deployment?()
A.
IPC Resource Calculator
B.
CTI Port Calculator
C.
Configuration and Ordering Tool
D.
CRS Applications Administration
【单选题】吴金婷 第五节 4、中国古代第一座开启活动式的石桥是()
A.
安济桥
B.
苏州宝带桥
C.
泉州洛阳桥
D.
潮州广济桥
【多选题】Cisco.com offers account managers which three of these resources? ()
A.
customer issue narratives
B.
training and events
C.
ordering information
D.
products and services information
【单选题】Assume there are three resources, R1, R2, and R3, that are each assigned unique integer values 15, 10, and 25, respectively. What is a resource ordering which prevents a circular wait?
A.
R1, R2, R3
B.
R3, R2, R1
C.
R3, R1, R2
D.
R2, R1, R3
【单选题】“山重水尽疑无路,柳暗花明又一村”采用的是 。
A.
借景
B.
夹景
C.
抑景
D.
对景
相关题目:
参考解析:
知识点:
题目纠错 0
发布
创建自己的小题库 - 刷刷题