● A network has been developed with resources from six different departments. One of the six departments has just informed you that they can increase the number of employees from 5 to 8. This will result in: A A shortening of the critical path.
B.
A shortening of the noncritical path.
D.
A decrease in the total cost of the project. D An increase in the cost of the project.
E.
A through D are possible based upon where the resources are deployed.