The duration optimization of the project network plan is through ( )
A.
Change the logical relation between the key work to make the calculated duration meet the requirement
B.
Change the logical relation between the key work to make the planned duration meet the requirement
C.
Compress the duration of key work to make the required duration meet the planned duration
D.
Compress the duration of key work to make the calculated duration meet the required duration